Ryan is building a treehouse it will take 13 1/4 hours to complete he can work on the treehouse 1 1/2 hours each day how many days will it take Complete up with the treehouse complete plzz help like now

User Abhilashv
by
4.6k points

1 Answer

0 votes

Answer:

9 days

Explanation:

13 1/4 / 1 1/2 = 8 5/6 so 9 days