In a company where manufacturing overhead is applied based on machine hours, the predetermined allocation rate is $3 per machine hour. Actual machine hours were 3,000 and actual manufacturing overhead was $8,000. Is overhead underallocated or overallocated and by how much?

1 Answer

5 votes

Answer:

The overhead is over allocated by $1000.

Explanation:

The manufacturing overhead is applied based on machine hours, the predetermined allocation rate is $3 per machine hour.

Actual machine hours were 3,000 making the cost as =
3000*3=9000dollars

But the actual manufacturing overhead was $8,000.

So, the overhead is over allocated by =
9000-8000=1000 dollars

Therefore, the answer is over allocated by $1000.