Answer and Explanation:
The computation of the future value in the following situations:
As we know that
Future value = Present value × (1 + rate of interest)^number of years
1. For semiannually
= $19,000 × (1 + 0.10 ÷ 2 )^8 × 2
= $19,000 × (1.05)^16
= $19,000 × 2.1829
= $41,475
2. For quartely
= $19,000 × (1 + 0.12 ÷ 4 )^2 × 2
= $19,000 × (1.03)^4
= $19,000 × 1.2268
= $23,309
3. For monthly
= $19,000 × (1 + 0.36 ÷ 12 )^15
= $19,000 × (1.03)^15
= $29,602