Answer:
The correct answer to the following question is $39,000 .
Step-by-step explanation:
The given information -
Direct material - $25,000
Beginning work in progress - $2000
Ending work in progress - $5000
Direct labor - $10,000
Manufacturing overhead - $7000
So to calculate the cost of goods manufactured =
Direct material + Beginning work in progress + Direct labor + Manufacturing Overhead - Ending work in progress
= $25,000 + $2000 + $10,000 + $7000 - $5000
= $39,000