Answer:
3 machine
Explanation:
It is given that 6 machine each working at the same rate can complete the work in 12 days
We the has to complete in 8 days
Let we need x extra machine to complete the work in 8 days
So total number of machines =x+6
Now according to man work day equation
![M_1D_1=M_2D_2](https://img.qammunity.org/2020/formulas/mathematics/high-school/uo54izv8ri4mfj6rbsd0chggyu0aqyaj42.png)
![6* 12=(x+6)* 8](https://img.qammunity.org/2020/formulas/mathematics/high-school/utmtaxer3f0peiq16qdilnvfg5glph51ki.png)
![8x+48=72](https://img.qammunity.org/2020/formulas/mathematics/high-school/khumrfn5g3um7maark8qxbdjuq7hjxmipy.png)
![8x=24](https://img.qammunity.org/2020/formulas/mathematics/middle-school/3dqgvuebim0lbihlv9c6089u4qbwuqmr8m.png)
x=3 machine