A company is interested in monitoring the variability in the weight of the fertilizer bags it produces. An appropriate control chart would be: a p-chart. a c-chart. an R-chart

User Thermans
by
4.7k points

1 Answer

7 votes

Answer:

The correct answer is "R-chart"

Step-by-step explanation:

The R-chart is a model that Indicates how the range of groups changes in a determined line of time. The R-chart is used to control process variability of the group, It is important to clarify that the units to compare, should be 10 or less.