Answer:
the standard for 1,900 units would be 4,180 labor hours
Step-by-step explanation:
From the budget we have the following relationship:
4,400 direct labor hours t produce 2,000 units
we divie to get the hours per unit
4,400 / 2,000 = 2.2 hours per unit
now we multiply by the amount of units produced
1,900 x 2.2 = 4,180
This is the standard labor hours for the actual production.