36.6k views
5 votes
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows:Year Cash Flow0 -$ 28,300 1 12,300 2 15,300 3 11,300 What is the NPV for the project if the required return is 11 percent?At a required return of 11 percent, should the firm accept this project?What is the NPV for the project if the required return is 25 percent?At a required return of 25 percent, should the firm accept this project?

1 Answer

4 votes

Answer:

NPV 3.461,36‬ at 11% discount rate, it should be accepted

NPV -2,882.4 at 25% discount rate, it should be rejected.

Step-by-step explanation:

We will calculate the present value of the cash flow at each discount rate.

First we will do 11% and then 25% discount


(inflow)/((1 + rate)^(time) ) = PV

Year 1 cash inflow: 12,300.00

time 1

rate 0.11


(12300)/((1 + 0.11)^(1) ) = PV

PV 11,081.08

Year 1 cash inflow: 15,300.00

time 2

rate 0.11


(15300)/((1 + 0.11)^(2) ) = PV

PV 12,417.82

Year 3 cash inflow: 11,300.00

time 3.00

rate 0.11


(11300)/((1 + 0.11)^(3) ) = PV

PV 8,262.46

Next, we add the project three years to get the total inflow.

Total value of the cash inflow:

11,081.08 + 12,417.82 + 8,262.46 = 31,761.36‬

Last, the net present value

present value of the cash inflow - investment

31,761.36 - 28,300 = 3,461.36‬

It is postive, this means the project yields at a better rate than 11%. The project should be accepted.

Now, we repeat for the second discount rate of 25%

Year 1 cash inflow: 12,300.00

time 1

rate 0.25


(12300)/((1 + 0.25)^(1) ) = PV

PV 9,840.00

Year 2 cash inflow: 15,300.00

time 2

rate 0.25


(15300)/((1 + 0.25)^(2) ) = PV

PV 9,792.00

Year 3 cash inflow: 11,300.00

time 3

rate 0.25


(11300)/((1 + 0.25)^(3) ) = PV

PV 5,785.60

Using a 25% discount rate, the present value of the cash inflow:

9,840.00 + 9,792.00 + 5,785.60 = 25,417.6

NPV: 25,417.6 - 28,300 = -2,882.4

User Elachance
by
8.4k points