Answer:
the total manufacturing overhead allocated is 610
Step-by-step explanation:
The computation of the manufacturing overhead allocated is as follows;
= Assembly department + sandling department
= 50 × 11 + 15 × 4
= 550 + 60
= 610
Hence, the total manufacturing overhead allocated is 610
We simply applied the above formula so that the total manufacturing allocated to Job 603 could come