Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint

A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time

User Hizmarck
by
4.7k points

1 Answer

5 votes

Answer:

The correct answer is A. Physical.

Step-by-step explanation:

A physical constraint is any mechanism, material or equipment attached to the body or near the body of a person that cannot be easily controlled or removed by itself and that prevents or is intended to prevent the free movement of a person's body to your choice and / or the normal access of a person to your body.