Answer:
6.4 minutes
Step-by-step explanation:
Average small tool per day = 445
working hours = 8 so that is 8*60 = (480 minutes)
Waiting time =
(image of the operation on the attach file)
=[445]/[(2*35)]
=445/70
=6.357 minutes