Answer:
The correct answer to the following question is D) in front of process B and C.
Step-by-step explanation:
Given information -
Capacity of process A - 20 units per hour
Capacity of process B - 25 units per hour
Capacity of process C - 30 units per hour
So here the total capacity per hour would be = 25 + 20 + 30 = 75 units
And average capacity per hour would be = 75 / 3 = 25 units
So from the given information it is quite clear that a manger doesn't need inventory in process B and C , as in both of these process capacity is equal to or more than average capacity per hour. But a manager would need inventory in process A because here total capacity is less than average capacity per hour.