Answer:
The correct answer to the following question is option A) $490,000.
Step-by-step explanation:
In 20X9, June 30 , the city of Moorhead went on to construct a new courthouse whose total budgeted cost was $500,000.
And in July 20X8, the project was given to Diamond construction to build the courthouse for $480,000. And on June 20X9, Diamond completed the courthouse and gave city of Moorhead a bill of $490,000, which they accepted and paid. So the city of moorhead should report their expenses as $490,000 on the statement of revenues, expenditures and fund balance.