Answer:
Equivalent Units of Production (EUP) = 3,520 units
Step-by-step explanation:
Units Completed = Beginning inventory units + Units Started - Ending Inventory
Equivalent Units of Production (EUP) = Beginning Work in Process (WIP) + Started and Completed Units + Ending Work in Process (WIP) x % of conversion
Units Completed = 200 + 3,200 - 400 = 3,000
EUP = 200 + 3,000 + 400 x 80% = 3,520