Requirements for the width of a tractor engine component are 23.23 +/- 0.612 millimeters. The current process produces components with an average width of 23.546 and a population standard deviation of 0.092. The process is normally distributed. If the control limits are set at +/- 2 standard deviations instead of +/- 3 standard deviations from the mean, what is the Cpk of this process?

User Zhekaus
by
5.6k points

1 Answer

1 vote

Answer:

The Cpk for the process is 1.61

Explanation:

The formula for Cpk is:


Cpk=min((USL-mean)/(2*stdDev),(mean-LSL)/(2*stdDev) )

In this case in specific that we can test the capability of the process for 2 standard dev we modify the formula to adjust it:

so for this formula:

average: 23.546

USL: 23.23+0.612=23.842

LSL: 23.23-0.612=22.618

standard dev=0.092

So,


Cpk=min((23.842-23.546)/(2*0.092) , (23.546-22.618)/(2*0.092) )\\[tex]Cpk=min(1.61 ,5.04 )\\\\Cpk=1.61\\\\[/tex]

The Cpk for the process is 1.61, so is a good indicator even with the control of two standard dev.