Answer:
c. $8.00 per unit
Step-by-step explanation:
Standard direct material cost per unit of finished product =
Raw material required for each unit of the product = 2 pounds
Therefore, raw material for 12,000 units of finished product = 12,000
2 = 24,000 pounds
Standard cost of 24,000 pounds of material for $4 per pound = 24,000
$4 = $96,000
Cost per unit of finished product =
![(Cost)/(Number \: of\: units) = (96,000)/(12,000) = 8](https://img.qammunity.org/2020/formulas/business/high-school/3fzehljb7yh1v5vsq9snc1vm1fp8j27z25.png)
c. $8.00 per unit