Answer:
MCE = 1/3 = 33.33%
Step-by-step explanation:
Value added acivities:
Throughput time 4.4 hours --> value added
Process time 1.1 hour --> value added
total time ading value 5.5 hours
total hours of the cycle
4.4 + 8.8 + 1.1 + 2.2 = 16.5 total time