Answer:
Total work in process = $12,900
Step-by-step explanation:
Provided information,
Cost incurred during the month on this order
Direct Materials = $2,100
Direct Labor = $3,600
Provided overheads are 200% of the direct labor cost = $3,600
200% = $7,200
Thus month end balance of work in process = $2,100 + $3,600 + $7,200
Total work in process = $12,900
Note: additional information regarding expenses to be incurred is to be ignored, and the above value is the value of work in process.
Total work in process = $12,900