A(n) ________ is a carefully predetermined cost that is usually expressed on a per unit basis.A) allocated cost B) applied costC) standard costD) flexible cost

1 Answer

4 votes

Answer: The correct Option is "C)."

A standard cost is a carefully predetermined cost that is usually expressed on a per unit basis.

Explanation: The "Standard Cost" is a budgeted cost that is based on normal efficiency levels, is developed based on budgeted direct and indirect costs and is a measure of how much it should cost to produce a unit of product or service always under conditions of efficiency , that is to say without waste.