It takes 15 men working steadily 4 days to dig the foundation for a new apartment. How many days would it have taken 25 men working at the same rate to dig the foundation? Express your answer as a decimal to the nearest tenth.]

1 Answer

6 votes

Answer:

2.4 days is the answer.

Explanation:

It takes 15 men working steadily 4 days to dig the foundation for a new apartment.

Let 25 men takes 'x' days to complete the same task.

Applying ratio we get:


(15)/(25) =(x)/(4)

Solving this we get;

=>
25x=60

So, x = 2.4 days