Answer:
Total Material Variance = $1,636 Favorable
Material Price Variance = $2,920 Unfavorable
Material Quantity Variance = $4,556 Favorable
Step-by-step explanation:
Total Material Variance = Standard Cost - Actual Cost
Standard Cost = Standard units
Standard Price
Standard Units = 10,300
2.9 = 29,870 units
Standard cost = 29,870
$6.8 = $203,116
Actual Cost = 29,200
$6.90 = $201,480
Total Material Variance = $203,116 - $201,480 = $1,636 Favorable
Material Price Variance = (Standard Rate - Actual Rate)
Actual Units
= ($6.8 - $6.9)
29,200 = - $2,920 Unfavorable
Material Quantity Variance = ( Standard Units - Actual Units)
Standard Price
= (29,870 - 29,200)
$6.8
= $4,556 Favorable
Final Answer
Total Material Variance = $1,636 Favorable
Material Price Variance = $2,920 Unfavorable
Material Quantity Variance = $4,556 Favorable