Which of the following factors could be included in a technical risk assessment? Select one: a. Cost of a new Web server b. Cost of hiring a Webmaster c. No previous experience with Java within the IS department d. Some fear of job loss among order entry department personnel e. All of these

User Vassilis
by
5.6k points

1 Answer

2 votes

Answer:

Option (c) No previous experience with Java within the IS department

Step-by-step explanation:

Option (c) No previous experience with Java within the IS department could be considered to include in the factors for technical risk assessment. Technical risk assessment contains the factors that are responsible for loss arising from technological procedures, engineering and design procedures followed. It also includes manufacturing procedures. Option (a) cannot be included because it is not a risk as it is a requirement for better functioning. Similarly, Option (b) and option (d) also cannot be included in the risk