As part of the ____________ phase, the customer may identify items that need to be corrected, which can require the team to re-plan parts of the project and then execute the revised activities.

User Mark Lu
by
4.6k points

1 Answer

5 votes

Answer:

Project Closing Phase, is the correct answer.

Step-by-step explanation:

It is the last phase in the project cycle. In this phase the project is closed and report of success is given to the sponsor. The deliverable are handed to the the customer, documentation is handed to the business, equipment and staff are released and stakeholders are informed about the closure of he project. Once the project has been closed and post implementation review is done for determining the success and identifying the lessons learned .