Preventive action ____________. a. modifies a nonconforming product or product subcomponent b. realigns the performance of the project work with the project management plan c. seeks to ensure the future performance of the project work is aligned with the project management plan d. is primarily addressed in the Control Quality process

User Jcaliz
by
8.3k points

1 Answer

1 vote

Answer: Option C

Explanation: Preventive action seeks to ensure the future performance of the project work is aligned with the project management plan.

In every management system there are some weaknesses, which might cause harm to the entity in future, to avoid such problems some actions are taken by the management called preventive action.