Answer:
total budgeted overhead is $28480
Step-by-step explanation:
Given data
production = 7900 units
overhead = $1.20 per unit
fixed factory overhead = $19,000
to find out
total budgeted overhead
solution
total budgeted overhead will be calculated by this formula i.e
total budgeted overhead is = variable factory overhead and + fixed factory overhead .......................1
variable factory overhead = production × overhead per unit
variable factory overhead = 7900 × 1.20
variable factory overhead = 9480
put all value equation in 1 we get
total budgeted overhead is = 9480 + 19000
total budgeted overhead is $28480