Answer:
The estimated expected (mean) time for project completion is 440 hours.
Step-by-step explanation:
The given breakdown structure is
Activity Precedes Optimistic Most Likely Pessimistic
A D 38 50 62
B E 90 99 108
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68
Using the table we get



The formula for estimated expected (mean) time for project completion is



Therefore the estimated expected (mean) time for project completion is 440 hours.