Answer:
The estimated expected (mean) time for project completion is 440 hours.
Step-by-step explanation:
The given breakdown structure is
Activity Precedes Optimistic Most Likely Pessimistic
A D 38 50 62
B E 90 99 108
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68
Using the table we get
![\sum t_0=38+90+85+19+91+62=385](https://img.qammunity.org/2020/formulas/business/college/w7t9vzrow9c27ebui4bfll5tid89buhdwb.png)
![\sum t_m=50+99+100+25+100+65=439](https://img.qammunity.org/2020/formulas/business/college/vh49qqc9zhtchmalsnwzwhexwa403cyp07.png)
![\sum t_p=62+108+115+31+115+68=499](https://img.qammunity.org/2020/formulas/business/college/220f8sut6riq42yp9c3cnax8io1jriidj9.png)
The formula for estimated expected (mean) time for project completion is
![t=(\sum t_0+4\cdot \sum t_m+\sum t_p)/(6)](https://img.qammunity.org/2020/formulas/business/college/qqwkul532avzvxi7cyk8dgdzzf15p43fte.png)
![t=(385+4\cdot 439+499)/(6)](https://img.qammunity.org/2020/formulas/business/college/awspw3dlj2zleqmn22aypcepey0dy35ssl.png)
![t=440](https://img.qammunity.org/2020/formulas/business/college/emxve85w8vd8yginj6vc98ogz5cij206a8.png)
Therefore the estimated expected (mean) time for project completion is 440 hours.