Which of the following is true about the job-order cost sheet?

a. It is prepared for every job.
b. It is the primary document for accumulating all costs related to a particular job.
c. It is subsidiary to the work-in-process account.
d. It contains all information pertinent to a job.
e. All of these choices are correct.

1 Answer

0 votes

Answer:

The correct answer is c) It is subsidiary to the work-in-process account

Step-by-step explanation:

It is used as an account book to the work in process account because it contains all details about the job in the process.