Answer:
The method 1 will have a bigger forecast bias ( whose value is 5 ) than the method 2 ( whose value 0 ).
Step-by-step explanation:
To know which method will have the bigger forecast bias , we will see the deviation of both methods from the actual forecast numbers and then by seeing which one is having a bigger deviation value , we can say which one is having bigger forecast bias.
FORECAST BIAS = ACTUAL NUMBER - FORECAST NUMBER
Actual Forecast Forecast Forecast Forecast
caller turn method 1 method 2 bias method 1 bias method 2
23 23 20 0 3
10 5 13 5 -3
15 14 14 1 1
19 20 20 -1 -1
TOTAL 5 0
from the above information we can say that the method 1 with forecast bias value of 5 is much bigger than the method 2 with forecast bias value of 0.