Which one of the following is a CMM level 5KPA?

o Software configurationmanagement

o Process changemanagement

o Peer reviews

o Processmeasurement

o Software projecttracking

1 Answer

3 votes

Answer:

o Process measurement

Step-by-step explanation:

CMM level 5 KPA

Key process areas of Level 5 address problems that need to be addressed by both the organisation and the projects in order to achieve ongoing and measurable software processes.

Key process areas-

  • Defect Prevention (DP)
  • Technology Change Management (TM)
  • Process Change Management (PC)