Which logical relationship does the PDM usemost often?

Start to finish
Start to start
Finish to finish
Finish to start

2 Answers

7 votes

Answer:

Finish to start

Step-by-step explanation:

I looked it :) hoped it helped

User Mike Burton
by
8.7k points
0 votes

Answer:

Finish to Start.

Step-by-step explanation:

Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM(Precedence Diagramming Method).For example :- in a software you cannot test a screen before it is developed,in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.