Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the project will take anywhere between 60 and 65 weeks to complete? (Round to two decimals.)

User Enthouan
by
5.3k points

1 Answer

2 votes

Answer: 0.3413

Explanation:

Given :Mean :
\mu=60\text{ weeks}

Standard deviation :
\sigma = 5\text{ weeks}

The formula for z -score :


z=(x-\mu)/(\sigma)

For x= 60 ,


z=(60-60)/(5)=0

For x= 65 ,


z=(65-60)/(5)=1

The p-value =
P(0<z<1)=P(z<1)-P(z<0)


= 0.8413447-0.5= 0.3413447\approx0.3413

Hence, the probability that the project will take anywhere between 60 and 65 weeks to complete = 0.3413.