74.2k views
0 votes
Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.50 per pound $ 7.50 Direct labor 5 hours at $7.50 per hour 37.50 Actual results: Units produced 7,800 units Direct material purchased 26,000 pounds at $2.70 $ 70,200 Direct material used 23,100 pounds at $2.70 62,370 Direct labor 40,100 hours at $7.30 292,730 Assume that the company computes variances at the earliest point in time. The standard hours allowed for the work performed are:

User Hirofumi
by
4.9k points

1 Answer

4 votes

Answer:

Standard hours for Job C77 39,000 HOURS

Step-by-step explanation:

We are asked for Direct labours, so everything else is irrelevant for now.

In the first sentence we got the stadard values for 1 units of product:

Cost Standard DL 5 hours at $37.5 for 1 unit of product

Now let's check how many units were done on job C77

Job C77 Unit Produced 7,800 units

If each units standard is 5 hours, then multiplying we get the standard hours for job C77

Standard hours for the work:


Actual units * StandardHours =$Standard Units JOB C77


7,800 * 5= 39,000

User PIIANTOM
by
5.3k points