204k views
4 votes
Araised flower bed requires 13 cubic feet of garden soil. You can get a good deal by importing the soil, but it is sold from the dealer in cubic meters. To the nearest hundredth, how many cubic meters of soil is needed? There are 3.28 feet in 1 meter.

User Greg Zuber
by
8.1k points

1 Answer

3 votes

Answer:

0.368 m^3

Step-by-step explanation:

3.28 feet = 1 m

Cube on both the sides

35.29 feet^3 = 1 m^3

So, 13 cubic feet = 13 / 35.29 m^3

= 0.368 m^3

User SkarE
by
9.0k points