Answer:
8 hours
Explanation:
Job v starts at time 0 and completes at time 3.
Job w starts at time 1 and completes at time 4.
Job x starts at time 4 and completes at time 8.
Job y starts at time 8 and completes at time 10.
Job z starts at time 10 and completes at time 15.
The average completion time is (3 +4 +8 +10 +15)/5 = 8 . . . hours.
_____
Comment on the schedule
Jobs v and x are the only ones completed by the time due. The latest is 8 hours late. If they are scheduled in order of due time, jobs v, w, and y can be completed by the due time; the others will be 4 and 6 hours late.