184k views
5 votes
The Environmental Protection Agency is attempting to revive 3 acres of contaminated soil by replacing the top 24 inches of the soil. Trucks with a hauling capacity of 28 cubic yards of soil are hired to remove the contaminated soil. How many full truckloads of contaminated soil will be hauled away?

1 Answer

3 votes

Answer:

346 trucks are needed

Explanation:

We know that one acre equals 43560 feet ^ 2

In this case the area is 3 acres. So:


3\ acres * (43,560\ ft^2)/(1\ acre) = 130,680\ ft^2

We know that 1 foot equals 12 inches. So:


24\ in * (1\ ft)/(12\ in) = 2\ ft

So the volume of the contaminated area is:


V = 2* 130,680\ ft^3\\\\V = 261,360\ ft^3

In a cubic yard there are 27 cubic feet. So:


28\ yard^2 * (27\ ft^3)/(1\ yard^3) = 756\ ft^3

Finally if we have a volume of
261,360\ ft ^ 3 and each truck can transport
756\ ft ^ 3 then the amount of trucks x we need is:


x = (261,360\ ft ^ 3)/(756\ ft ^ 3) = 346\ trucks

User Musab Bozkurt
by
4.8k points