Which employee's path is the critical path on this activity graph? Explain how you know that this employee's path is the critical path.

Which employee's path is the critical path on this activity graph? Explain how you-example-1
User Dease
by
6.2k points

1 Answer

3 votes

Answer:

Jim's path is the critical path on this activity graph.

Explanation:

Critical Path:

Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.

In given case:

Path 1 Bill task's total duration= 6 days

Path 2 Jim's task's total duration= 17 days

Path 3 Betty task's total duration= 7 days

Path 4 Cynthia task's total duration= 14 days

Hence the longest path i.e. critical path is of Jim's activity path !