Which of the following is a bottom-lined statement for a progress report?

2 Answers

2 votes

Answer:

C

Step-by-step explanation:

As of April 30, our project is.......

User Raj Shekhar
by
6.2k points
4 votes

Answer:

as of April 30 our project is on a budget but two-weeks behind schedule

Step-by-step explanation: