He best cost estimate for resources required to handle production runs is developed by using ________ as the denominator for activity cost driver calculations.

1 Answer

2 votes

Practical capacity.

Determining practical capacity is a judgement process to help avoid distortions of assigning costs where they don't belong (like to the customer or to the products themselves)