205k views
5 votes
Solve Que no. 1 .....wid detailed​

Solve Que no. 1 .....wid detailed​-example-1

1 Answer

1 vote

Answer:

1/2 hour per day.

Explanation:

Using proportion:

200 men make the embankment 5 km long in 25 days

1 man .............................................5 km ...... in 25*200 days

1 man ...............................................2 km ....... in 2/5 * 25*200= 2000 days

At this rate 60 men will finish the work in 2,000 / 60 = 33 1/3 days.

If they make it in 32 days they will have to work 1 /1/3 days overtime which is 16 hours'

So they have to work an extra 1/2 hour per day.