Answer:
= Sh. 2281.50
Explanation:
Area of the path;
(126 × 2.5 ) + (2.5 × (48 - (2.5×2)
= 315 + (2.5 × 43)
= 315 + 107.5
= 422.5 m²
But; the cost of graveling is sh 5.40 per square meter
Therefore; The cost of graveling the whole path;
= 422.5 × 5.40
= Sh. 2281.50