108k views
2 votes
4 men and 6 boys can finish a piece work in 5 days while 3 men and 4 boys can finish it in 7 days. find the time taken by 1 man alone or that by 1 boy alone.

1 Answer

2 votes

Answer:

Number of days taken by 1 man alone and 1 boy alone are 35 days and 70 days respectively.

Explanation:

Let, the work completed by 1 man in 1 day = x and the work completed by 1 boy in 1 day = y.

So, 4 men and 6 boy's 1 day work is
(4)/(x) and
(6)/(y)

And, 3 men and 4 boy's 1 day work is
(3)/(x) and
(4)/(y)

Since, 4 men and 6 boys complete the work in 5 days and 3 men and 4 boys complete the work in 7 days.

So, we have,


(4)/(x)+(6)/(y)=(1)/(5)


(3)/(x)+(4)/(y)=(1)/(7)

Let,
u=(1)/(x) and
v=(1)/(y)

So, the equations are,


4u+6v=(1)/(5) ................(1)


3u+4v=(1)/(7) ................(2)

Multiply (1) by 3 and (2) by 4 and subtract the equations, we get,


2v=(1)/(35) i.e.
v=(1)/(70) i.e.
(1)/(y)=(1)/(70) i.e. y = 70.

Substitute value of 'v' in (1) gives,


4u+(6)/(70)=(1)/(5) i.e.
4u=(-6)/(70)+(1)/(5) i.e.
4u=(8)/(70) i.e.
u=(8)/(70* 4) i.e.
u=(1)/(35) i.e.
(1)/(x)=(1)/(35) i.e. x = 35

So, the number of days taken by 1 men alone and 1 boy alone are 35 days and 70 days respectively.

User Meika
by
6.5k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.