108k views
2 votes
4 men and 6 boys can finish a piece work in 5 days while 3 men and 4 boys can finish it in 7 days. find the time taken by 1 man alone or that by 1 boy alone.

1 Answer

2 votes

Answer:

Number of days taken by 1 man alone and 1 boy alone are 35 days and 70 days respectively.

Explanation:

Let, the work completed by 1 man in 1 day = x and the work completed by 1 boy in 1 day = y.

So, 4 men and 6 boy's 1 day work is
(4)/(x) and
(6)/(y)

And, 3 men and 4 boy's 1 day work is
(3)/(x) and
(4)/(y)

Since, 4 men and 6 boys complete the work in 5 days and 3 men and 4 boys complete the work in 7 days.

So, we have,


(4)/(x)+(6)/(y)=(1)/(5)


(3)/(x)+(4)/(y)=(1)/(7)

Let,
u=(1)/(x) and
v=(1)/(y)

So, the equations are,


4u+6v=(1)/(5) ................(1)


3u+4v=(1)/(7) ................(2)

Multiply (1) by 3 and (2) by 4 and subtract the equations, we get,


2v=(1)/(35) i.e.
v=(1)/(70) i.e.
(1)/(y)=(1)/(70) i.e. y = 70.

Substitute value of 'v' in (1) gives,


4u+(6)/(70)=(1)/(5) i.e.
4u=(-6)/(70)+(1)/(5) i.e.
4u=(8)/(70) i.e.
u=(8)/(70* 4) i.e.
u=(1)/(35) i.e.
(1)/(x)=(1)/(35) i.e. x = 35

So, the number of days taken by 1 men alone and 1 boy alone are 35 days and 70 days respectively.

User Meika
by
5.0k points