Bob the builder is making 480kg on concrete mix. Concrete is made by mixing cement, sand and gravel in the ratio 1 : 3 : 4. How much sand does he need?

User DustInComp
by
4.9k points

2 Answers

5 votes

Answer:

the answer is 180

Explanation:

User AdvSphere
by
4.2k points
1 vote

Answer:

The amount of sand builders need is 180 kg.

Explanation:

It is given that the Bob the builder is making 480 kg on concrete mix. Concrete is made by mixing cement, sand and gravel in the ratio 1 : 3 : 4.

Let the amount of cement, sand and gravel is x, 3x and 4x respectively.

Since Bob the builder is making 480 kg on concrete mix, therefore


x+3x+4x=480


8x=480

Divide both sides by 8.


x=60

The value of x is 60.

The amount of sand is 3x.


3x=3* 60=180

Therefore the amount of sand builders need is 180 kg.