Workers install 600 chairs at a constant rate. After 4 days, the workers still have to install 360 chairs. How much time does it take to install the chairs from start to finish?

User Ihkawiss
by
5.4k points

2 Answers

6 votes
It’ll take them 2.4 days to install 360 chairs
User Stas Boyarincev
by
5.4k points
3 votes

Answer:

6 days and 18 hours

Explanation:

Given that after 4 days, the workers still have to install 360 chairs, it is expected that as time in days increases, the number of chairs installed increases as well. This is a direct proportionality between both measures.

If after 4 days, the workers still have to install 360 chairs then 600 chairs would be installed in

= 600 * 4/360 days

= 6 2/3 days

= 6 days and 18 hours