Answer:
Team worked for 12 days.
Explanation:
Let d be the number of days.
We have been been given that to fulfill an assignment by a given deadline, a team of workers had to produce 54 parts daily. So the number of parts produced in d days will be
.
After exceeding the the schedule by 6 parts per day number of parts produced in will be
parts per day.
As after exceeding the schedule by 6 parts per day, team finished the assignment 1 day earlier, so number of days will be d-1.
So after exceeding the schedule the total number of parts produced in d days will be

We are also told that exceeding the schedule by 6 parts per day, the team produced 18 extra parts.
We can represent this information in an equation as:

Let us solve for d by combining like terms.



Upon dividing both sides of our equation by -6 we will get,


Therefore, before exceeding the schedule team will finish the assignment in 13 days.
As team finished the assignment 1 day earlier, so number of days taken by team will be:


Therefore, after exceeding the schedule by 6 parts per day, the team took 12 days to complete the assignment.