Answer:
15 days
Explanation:
Let x be the number of days needed for B to complete the job. Then x-5 is the number of days needed for A to complete the job.
In 1 day,
- A completes
of all work; - B completes
of all work.
Hence, in 1 day both A and B complete
of all work. A and B working together can do a work in 6 days. Then
![6\cdot \left((1)/(x-5)+(1)/(x)\right)=1.](https://img.qammunity.org/2020/formulas/mathematics/high-school/vq97x75lpw4sgahy4wuzmhh5abx60141oy.png)
Solve this equation:
![(6x+6x-30)/(x(x-5))=1,\\ \\12x-30=x^2-5x,\\ \\x^2-17x+30=0,\\ \\D=(-17)^2-4\cdot 30=289-120=169=13^2,\\ \\x_(1,2)=(17\pm 13)/(2)=2,\ 15.](https://img.qammunity.org/2020/formulas/mathematics/high-school/l0ojjvmp6fputki12daizu7tqy9r5nl4ku.png)
If
then
that is impossible. So, B needs 15 days to complete the work alone.