190k views
0 votes
A and B working together can do a work in 6 days. If A takes 5 days less than B to finish the work, in how many days B alone can do the work.

User Pablomarti
by
8.2k points

1 Answer

5 votes

Answer:

15 days

Explanation:

Let x be the number of days needed for B to complete the job. Then x-5 is the number of days needed for A to complete the job.

In 1 day,

  • A completes
    (1)/(x-5) of all work;
  • B completes
    (1)/(x) of all work.

Hence, in 1 day both A and B complete
(1)/(x-5)+(1)/(x) of all work. A and B working together can do a work in 6 days. Then


6\cdot \left((1)/(x-5)+(1)/(x)\right)=1.

Solve this equation:


(6x+6x-30)/(x(x-5))=1,\\ \\12x-30=x^2-5x,\\ \\x^2-17x+30=0,\\ \\D=(-17)^2-4\cdot 30=289-120=169=13^2,\\ \\x_(1,2)=(17\pm 13)/(2)=2,\ 15.

If
x=2, then
x-5=-3 that is impossible. So, B needs 15 days to complete the work alone.

User Green Falcon
by
9.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.