190k views
0 votes
A and B working together can do a work in 6 days. If A takes 5 days less than B to finish the work, in how many days B alone can do the work.

User Pablomarti
by
5.4k points

1 Answer

5 votes

Answer:

15 days

Explanation:

Let x be the number of days needed for B to complete the job. Then x-5 is the number of days needed for A to complete the job.

In 1 day,

  • A completes
    (1)/(x-5) of all work;
  • B completes
    (1)/(x) of all work.

Hence, in 1 day both A and B complete
(1)/(x-5)+(1)/(x) of all work. A and B working together can do a work in 6 days. Then


6\cdot \left((1)/(x-5)+(1)/(x)\right)=1.

Solve this equation:


(6x+6x-30)/(x(x-5))=1,\\ \\12x-30=x^2-5x,\\ \\x^2-17x+30=0,\\ \\D=(-17)^2-4\cdot 30=289-120=169=13^2,\\ \\x_(1,2)=(17\pm 13)/(2)=2,\ 15.

If
x=2, then
x-5=-3 that is impossible. So, B needs 15 days to complete the work alone.

User Green Falcon
by
6.0k points