Answer: 28 %
Explanation:
Since, Volume of a work = productivity × time × number of workers
Let V be the initial volume of the work , p is the initial productivity , n is the initial time and x be the initial number of workers.
Then, V = p × N × x ------ (1)
When, the volume of construction work was increased by 60%, productivity of labor increased by only 25% and time remains same,
Let y be the new number of workers,
Then, 1.6 V = 1.25 p × N × y -------(2)
Dividing equation (1) by equation (2)
We get,




Thus, the percentage increase in the number of workers =






Therefore, the number of workers is increased by 28%.