The volume of construction work was increased by 60% but the productivity of labor increased by only 25%. By what percent must the number of workers be increased in order for the work to be completed in time, as it was scheduled originally?

User Dallonsi
by
8.4k points

2 Answers

5 votes

Answer: The number of number of workers is increased by 28%.

Explanation:

Let the volume of construction work be v

Let the productivity of labor be p.

Let the number of workers be n.

So, our original equation becomes


v=p* n

Now,

According to question, we have given that if volume increased by 60% and the productivity increases by 25%.

Let the percentage increase in number of workers be x

So, it becomes,


(100+60)/(100)* v=(100+25)/(100)* p* n(1+x)\\\\1.6* v=1.25* p* n(1+x)\\\\1.6* p* n=1.25* p* n(1+x)\\\\(1.6)/(1.25)=1+x\\\\1.28=1+x\\\\1.28-1=x\\\\x=0.28

So, The number of number of workers is increased by 28%.

User Nubaslon
by
8.7k points
6 votes

Answer: 28 %

Explanation:

Since, Volume of a work = productivity × time × number of workers

Let V be the initial volume of the work , p is the initial productivity , n is the initial time and x be the initial number of workers.

Then, V = p × N × x ------ (1)

When, the volume of construction work was increased by 60%, productivity of labor increased by only 25% and time remains same,

Let y be the new number of workers,

Then, 1.6 V = 1.25 p × N × y -------(2)

Dividing equation (1) by equation (2)

We get,


(1)/(1.6) = (x)/(1.25y)


1.25 y = 1.6 x


y = (1.6x)/(1.25)


y = (160x)/(125)

Thus, the percentage increase in the number of workers =
(160x/125-x)/(x)* 100


(160x-125x)/(125x)* 100


(35x)/(125x)* 100


(35)/(125)* 100


(3500)/(125)


28\%

Therefore, the number of workers is increased by 28%.


User Samarth Hattangady
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories