The _____ describes how changes to the project's scope will be submitted, logged, and reviewed. Group of answer choices Quality Management Plan Communications Plan Human Resources Plan Change Management Plan Scope Management Plan

User Gao
by
2.3k points

1 Answer

19 votes
19 votes

Answer:

Communication Plan Communication plan is made to communicate the important information to stakeholders throughout the project.