Answer:
1/6 of the third workers time
Explanation:
one of the people is budgeted for 1 /2 of his time to the project and a second person for 1/3 of her time
Let x be the third workers time
Let the completed job time = 1
Time taken for 3 workers to complete the job = 1
![(1)/(2)+ (1)/(3) + x= 1](https://img.qammunity.org/2020/formulas/mathematics/middle-school/6fj0e34x2nt39s5ga2ar3f9ppyzg3xz3ax.png)
now we solve for x
LCD = 2*3 = 6
We multiply the whole equation by 6
![(1)/(2)*6+ (1)/(3)*6 + x*6= *6](https://img.qammunity.org/2020/formulas/mathematics/middle-school/j8znv2e3caifmwvcyickx0eocvogxfrr0n.png)
3 + 2 +6x = 6
5 + 6x = 6
subtract 5 on both sides
6x = 1
divide both sides by 6
![x= (1)/(6)](https://img.qammunity.org/2020/formulas/mathematics/middle-school/b7yp9tvqeva55230jtzi6z0iphpx5nwck0.png)