8. There are 3 people who work full-time and are to work together on a project, but their total time on the project is to be equivalent to that of only one person working full-time. one of the people is budgeted for 1 /2of his time to the project and a second person for 1/3 of her time, what part of the third worker’s time should be budgeted to this project?

1 Answer

1 vote

Answer:

1/6 of the third workers time

Explanation:

one of the people is budgeted for 1 /2 of his time to the project and a second person for 1/3 of her time

Let x be the third workers time

Let the completed job time = 1

Time taken for 3 workers to complete the job = 1


(1)/(2)+ (1)/(3) + x= 1

now we solve for x

LCD = 2*3 = 6

We multiply the whole equation by 6


(1)/(2)*6+ (1)/(3)*6 + x*6= *6

3 + 2 +6x = 6

5 + 6x = 6

subtract 5 on both sides

6x = 1

divide both sides by 6


x= (1)/(6)



User Ahmed Abbas
by
8.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories