Answer:
d. $72.41 per setup
Step-by-step explanation:
The computation of the activity rate for the machine setup activity pool is as follows;
The Activity rate for the Machine setups activity cost pool is
= Estimated overhead cost ÷ Total machine setup
= $50,687 ÷ 700
= $72.41 per setups
Hence, the activity rate for the machine setup activity pool is $72.41 per setup
Therefore the option d is correct